Construction is underway on the Swift Green Line, Community Transit's second bus rapid transit route.

Work has started on the 34 Swift stations that will line the corridor between Bothell and Boeing. Construction is also underway on a new transit center near Boeing and a road widening project near the I-5 overpass along 128th Street in south Everett. The Swift Green Line is scheduled to open for service in early 2019.

The Swift Network News newsletter is published weekly to provide the latest construction updates about the Swift Green Line, which includes these projects:


Swift Network News

Issue 28, Volume 2 | February 16, 2018

Temporary signage on eastbound 128th will be replaced.In this issue:

  • 128th Street: Permanent Traffic Signs Coming to West Side of I-5
  • Community Transit LiveNext Live Construction Update Wednesday at Noon
  • Seaway Transit Center: Traffic Poles Coming to North Side of 75th Street
  • Swift Green Line Stations: Two More Area 1 Stations to Complete First Stage of Construction
  • Construction Overview: Station Construction is Divided into Four Areas With Work Done in Stages
View this issue online now
Download the PDF
Subscribe to receive this newsletter here.

Issue 27, Volume 2 | February 9, 2018

Drainage work at eastbound 128th St. SW and 4th Ave. W.In this issue:

  • Swift Green Line Stations: Work Begins on Stations at 128th St. SW and 4th Ave. W
  • Seaway Transit Center: Concrete Seat Walls and Concrete Light Pole Foundations Installed
  • 128th Street: Drainage Work Continues East of I-5
  • Community Transit LiveGet Your Live Construction Update Along With Lunch: Noon, Feb. 22
  • Construction Overview: Station Construction is Divided into Four Areas With Work Done in Stages
View this issue online now
Download PDF
Subscribe to receive this newsletter here.

Issue 26, Volume 2 | February 2, 2018

Crews pour concrete for a new sidewalk along the south side of 75th St., then ensure a smooth finish and 1.2 percent slope.In this issue:

  • Seaway Transit Center: Sidewalk Nearly Complete Along South Side of 75th St.
  • Swift Green Line Stations: Station Construction Begins in Area 2
  • 128th Street: East Side Grading Beings the Preparations for Concrete
  • Community Transit LiveGet Your Live Construction Update Along With Lunch: Noon, Feb. 22
  • Construction Overview: Station Construction is Divided into Four Areas With Work Done in Stages
View this issue online now
Download PDF
Subscribe to receive this newsletter here.



Past Issues of Swift Network News

Swift Network News

Issue 28, Volume 2 | February 16, 2018
Issue 27, Volume 2 | February 9, 2018
Issue 26, Volume 2 | February 2, 2018
Issue 25, Volume 2 | January 26, 2018
Issue 24, Volume 2 | January 19, 2018
Issue 23, Volume 2 | January 11, 2018
Issue 22, Volume 2 | January 5, 2018
Issue 21, Volume 2 | December 28, 2017
Issue 20, Volume 2 | December 15, 2017
Issue 19, Volume 2 | December 8, 2017
Issue 18, Volume 2 | December 1, 2017
Issue 17, Volume 2 | November 17, 2017
Issue 16, Volume 2 | November 10, 2017
Issue 15, Volume 2 | November 3, 2017
Issue 14, Volume 2 | October 26, 2017
Issue 13, Volume 2 | October 19, 2017
Issue 12, Volume 2 | October 12, 2017
Issue 11, Volume 2 | September 28, 2017
Issue 10, Volume 2 | September 15, 2017
Issue 9, Volume 2 |August 31, 2017
Issue 8, Volume 2 |August 18, 2017
Issue 7, Volume 2 |August 7, 2017
Issue 6, Volume 2 | July 21, 2017
Issue 5, Volume 2 | July 7, 2017
Issue 4, Volume 2 | June 23, 2017
Issue 3, Volume 2 | June 9, 2017
Issue 2, Volume 2 | May 25, 2017
Issue 1, Volume 2 | May 11, 2017